DBC PORTFOLIO

Project

Childrens Hospital Expansion

Seattle, WA

Owner

Childrens Hospital

Architect

H.K.S., Inc., Dallas, TX

Engineer

C.D.I. Engineers, Lynnwood, WA

General Contractor

Sellen Construction, Seattle, WA

Project Description

DBC joined forces with Sellen Construction to build this new Ambulatory Care Building at Children’s Hospital. The work involved demolition of 2 existing buildings and replacement with a new state of the art facility.

DBC’s portion of the work is valued at $12.5 Million, and involved a work force of up to 100 skilled craftsmen for a period of 2 years. The work scope included 2 large mechanical rooms, HVAC duct fabrication and installation, plumbing, medical gas, installation of 3 very large roof mounted penthouse HVAC units.

DBC's scope of work also includes renovation of the existing facility that is continuing to provide 24 hour patient care.  Work of this nature requires close coordination with hospital staff to minimize impact on patients and staff.

Project Challenges & Solutions

One of the unique challenges DBC faced on this project was the extremely limited space for material storage and staging. DBC was allocated an area measuring 8 X 24 feet for storage of all materials, equipment, ducting and fixtures. This necessitated a “just in time” delivery system and exceptionally close planning and scheduling.

Portfolio Index

 

CLICK TO ENLARGE

The Whale
Attrium duct work

 

Air Handler Exterior
Air Handler Interior

Chiller Unit
G wing pipiing

East Side Courtyard
West Side ACB